Eastern Section including Roofing for
Four-Step Section of 40,000 square feet:
1. Repair cracks on east exterior wall
2. Patch floor
3. Remove carpets / Install floor
tiles
4. Hang sheet rock, tape and sand
5. Install new windows
6. Install down spout splash
7. Weld and repair entry doors on south wall
8. Install new door handles and locks
9. Install freeze-proof faucets
Material Needs:
1. 25 tubes caulking
2. 150 gallons interior primer and semi-gloss paint
3. Materials to patch floors
4. 20,000 square feet of carpet
5. 50 sheets of sheet rock [1/2 x 4 x 12]
6. 50# sheet rock nails / screws
7. 30 2 x 4 x 16 pine panels
8. Roofing materials to cover 40,000 square feet
9. Windows Safety Wired Mash Plate Glass
a. 3 each -- Ό x 14 ½ x 19 ½
b. 1 each Ό x 15 ½ x 19 ½
c. 1 each Ό x 7 x 25
10. 8 each down spout splash 12 x 48
Southern Section:
1. Install safety wired mash plate glass 4 each 7 x 39
2. Install freeze-proof faucets
3. Install new door handles and locks
Material Needs
1. 4 each 7 x 39 safety wired mash plate glass
2. 2 freeze proof faucets
3. 2 sets door handles and locks
Western Section:
1. Install outdoor security lights and outlets
2. Install safety wire mash glass plates
3. Weld and repair double entry doors
4. Install handles and locks
5. Repair utility doors
6. Install new ceiling light
Material Needs
1. 8 each -- Outdoor security lights
2. 5 each security outlets
a. Locks for entry doors
3. Frame cast and lattice screen for utility doors
4. Ceiling light
Northern Section:
1. Install safety wired mash plate glass
a. 2 each Ό x 14 ½ x 19 ½
b. 1 each 15 ½ x 19 ½
Other Interior Work:
1. Install lighted exit signs
2. Install new alarm system
3. Install 20 new ceiling lights
4. Lower four ceiling heaters
5. Install 4,000 feet of commercial vinyl base
6. Install 40,000 square feet of drop ceiling
7. Install new fire extinguishers
Material Needs
1. 6 each Exit signs
2. 20 new ceiling lights
3. 4,000 feet commercial 4 vinyl base
4. 30 tubes adhesive
5. 40,000 square feet of dropped ceiling hardware and tiles
6. 16 each new fire extinguishers
Restrooms:
1. Replace toilets
2. Update toilet panels and doors
3. Adjust urinals
Material Needs
1. 9 full size toilets
2. 2 full size handicap toilets
3. New toilet panels and doors
|
Kitchen Area:
1. Install new fluorescent ceiling lights
2. Install new refrigerators and sinks
3. Install new heater
4. Install new smoke sensors
5. Clean and repair ceramic tile
6. Remove or repair floor electric conduit
7. General plumbing update
8. Install new gas line connection to stoves
9. Clean or replace hood vents
10. Repair double door and install knobs and locks
Material and Equipment Needs
1. 4 regular refrigerators or 2 commercial
2. 2 each stainless commercial sinks
3. 3 each Smoke Sensors
4. Ceramic tiles
5. General plumbing supplies
6. Door locks and knobs
Gym:
1. Install safety glass
2. Install new metal doors with hinges and locks
3. Install new door knobs and locks
4. Clean smoke damage / repair / floor tiles / repaint
inside gym
Materials Needed
1. Safety glass
a. 4 each Ό x 19 x 24
b. 2 each 19 x 22
2. 8 each 36 x 84 metal doors with hinges and locks
3. Commercial door handles
4. Paint
Secretarys Office:
1. Install clear safety glass
2. Install new metal door cases
3. Install new medicine cabinet
4. Replace laminated wall cabinet doors and drawers
5. Replace outlet and switch covers with stainless covers
Materials Needed
1. Clear safety glass plate
a. 1 each Ό x 45 ½ x 34
b. 1 each 24 x 34
c. 1 each 21 x 31 ½
2. 1 each medicine cabinet
3. 2 each Ύ x 14 x 17 ½ laminated wall cabinet doors
4. 1 each 8 x 17 ½ drawer facing
MDF:
1. Remove or put electrical wire to use
2. Replace Door casings
3. Update AC condenser
Material Needs
1. New air conditioner condenser
2. 2 sets of 36 x 84 door casings
Training Center:
1. Paint classrooms
2. Replace carpet with carpet tiles
Material Needs
1. 24 each 4 x 6 windows
2. 200 classroom chairs
3. PA system
4. Office furniture
5. Good computers
6. Bunk beds for mission teams use
7. Floor tiles for 12 each 30 x 30 classrooms\remove
old carpet
Exterior
1. Paint exterior
Material Needs
1. Exterior
primer (50 or 60) 5 gallon cans
2. Exterior Paint (50 or 60) 5 gallons cans
|